Oceanic Bridge Replacement: Navesink River Road Roundabout Plans

October 22, 2026

"Unless the county was willing to fund it with taxpayer dollars, we really had no choice but to move forward with that option," Monmouth County engineer Joseph M. Ettore said at the September 29 public session, as The Two River Times reported. He meant the replacement Oceanic Bridge's 65-foot fixed clearance, the figure the U.S. Coast Guard recommended in 2019 and that county officials, Middletown and former Gov. Phil Murphy all pushed back on in later years.

In the preliminary design, the bridge lands on the Rumson shore right where it does today. On the Middletown shore, the landing moves, the traffic signal comes out, and the old entrance becomes public waterfront. Most of what the county showed on September 29 happens on Navesink's side of the river.

Rumson keeps its footprint, and the Middletown end moves north

The Two River Times reported that the new bridge will follow the existing footprint on Bingham Avenue in Rumson. On the Middletown side, the entrance will sit slightly north of where it is now, and the current entrance will become a recreational area with public waterfront access.

The county's meeting FAQ describes that area in more detail. It would have a 20-foot-wide promenade with parallel parking along it. A roundabout at its entrance would let cars pull out more safely than a stop sign would.

That puts a new public place to stand at the water's edge on the Middletown shore of the Navesink, near the base of the longest bridge in Monmouth County. Today's span is 2,712 feet long.

The signal at Navesink River Road becomes a roundabout

The second roundabout will matter more day to day. It replaces the traffic light where Locust Point Road meets Navesink River Road. Ettore called that a "high crash location" and said, as reported by The Two River Times, that "the roundabout slows traffic down, and it reduces serious injury by 78%." He pointed to the county's other roundabouts at Brookdale, Colts Neck and Interlaken.

The county's presentation slides say the new alignment gets rid of the existing "substandard curves." The posted speed limit drops to 35 mph within the project limits. The FAQ also calls this roundabout "a visual gateway transition point" for drivers crossing in either direction.

This is the part of the plan that drew comments from the neighborhood. The paper reported that several Middletown residents, mostly from the Navesink section, raised concerns at the session. They asked how the roundabout would affect people who live nearby and how the path would reach Rumson's Victory Park without disrupting local traffic.

The bridge you cross now, and the one in the plans

Here is the current bridge next to the preliminary preferred alternative, using the county's materials and the newspaper's coverage:

Oceanic Bridge today Preliminary replacement
Type Double-leaf bascule drawbridge, built 1939 Fixed span
Clearance over water 22 feet at mean high tide when closed 65 feet
Roadway height at the top Not applicable 81 feet
Length 2,712 feet More than 3,000 feet
Pedestrian space Two 6-foot sidewalks, no shoulder One 14-foot shared-use path on the west side, with a barrier
Travel lanes 12 feet 11 feet
Middletown intersection Traffic signal at Navesink River Road Roundabout

Ettore said the 65-foot figure matches the Route 36 Highlands-Sea Bright Bridge at the mouth of the Navesink. Keeping both bridges at the same clearance means any boat that can reach the river can also get past the Oceanic. The slides also list lower ongoing maintenance and operating costs as a reason for the fixed design.

The path reaches Navesink first, and Rumson's connection is still open

Ettore said the narrower lanes don't reduce the bridge's vehicle capacity. The space they free up goes to a 14-foot path for people walking and biking, with scenic overlooks and a slightly gentler slope. He added that overhead lighting will likely go in on both sides, though it isn't shown on the plans. "The bridge has always been actively used by pedestrians and cyclists," he told the paper.

Because the path runs on the west side, it leads straight onto the new promenade on the Middletown shore. The Rumson end has three options on the table, according to the county's presentation boards:

  1. A 14-foot path from Bingham Avenue to River Road. This would convert existing parking to angled spaces, remove five spaces and make traffic one-way.
  2. A 10-foot path from the bridge to Hunt Street, which connects to Victory Park.
  3. A riverfront path from the bridge to Washington Street.

The paper noted that the path is about 17 feet up where it reaches Rumson, so any of the three options would need ramps. For a Navesink walker or cyclist, the near end of the crossing is the settled part of the plan. Where the path comes down in Rumson is still being decided.

The old drawbridge carries the traffic for years yet

None of this changes how you cross the river this winter. The county's FAQ says the existing bridge will stay in service while the new one goes up, with detours "kept to a minimum." Construction is expected to take at least three years. Staging and detour details will be worked out during final design.

The schedule has also moved since late summer. A preview published September 26 put final design in spring 2027, groundbreaking around 2029 and completion in 2031. The county's September 29 slides now say preliminary engineering wraps up in fall 2027 and final design starts in spring 2028. The construction start is listed as "To Be Determined."

Meanwhile, the 1939 span keeps running on its current rules. The U.S. Department of Transportation classified it as structurally deficient in July 2021, and the drawbridge has often broken down in summer, leaving it stuck open. This past July 2, a Coast Guard bulletin reported the opposite problem. Heat expansion had left the bridge stuck in the closed position.

The county's bridge page lists the seasonal schedule. From April 1 through November 30, the bridge opens on signal. From December 1 through March 31, an opening needs 24 hours' notice. That means drivers have about a month left of on-signal openings before the winter rules start.

Comments close Friday

This post goes up Thursday, October 29. The county is taking written comments on the preliminary plans through Friday, October 30, 2026, according to the public meeting notice. Comments can go to the county in any of these ways:

  • Email: [email protected]
  • Online: the Contact Us form on the project website
  • Mail: Michael Ruggiero, P.E., Monmouth County Division of Engineering, Hall of Records Annex, 1 East Main Street, 3rd Floor, Freehold, NJ 07728
  • Hotline: 732-701-3359, for questions and comments

The slides, boards and FAQ from the session are on the project site. The county says a formal report on the meeting will be posted after the comment period ends. The Borough of Rumson's recap covers the same topics from the other shore, including the Victory Park connections and construction staging.

Kate Raftery follows projects like this one because the roads, paths and waterfront at the end of a street shape daily life in Navesink long before they're finished. If you'd like to talk through how the new Navesink River Road roundabout or the waterfront area could affect your corner of the neighborhood, Katherine Raftery is glad to sit down with you. Let's Connect.